Three year plan


2016-19 Plan for Physical Improvements for 900 Marshy Cove

Mission: To create a safe, secure, and aesthetically appealing place to live.
Purpose of this plan: To list improvements for the next three years and assigned time lines for their accomplishment.
1.      Business practices(2016-2018)

a.      Evaluate the purchase practices of Sentry & 900 MC (2016-17)

                                                              i.      Specification process, bid collection, and selection

                                                            ii.      Term and conditions

                                                          iii.      Purchase orders, work orders

                                                           iv.      Vendors’ insurance coverage, liabilities,

b.      Develop a heads up budgeting process (2016)

                                                              i.      Identify previous years variabilities

                                                            ii.      Identify new needs into the budget

                                                          iii.      Minimize any increases to the monthly assessment

                                                           iv.      Head-off any need for future special assessments.

c.       Communicate with the Deep Harbour Master Association- on going

                                                              i.      Identify improvements that are the responsibility of DHMA that affect 900 MC

                                                            ii.      Review contract with DHMA to ensure that 900 MC gets its fair share

                                                          iii.      Articulate our concerns to the AHMA at their regular and annual meetings.

2.      Deck Repairs (2016-2017)

a.      Find a cost effective solution to the deck edge curling seen on 25 of 48 units to date.

b.      Short term fix: glue down all units; cost goal $100-$300 per deck,

                                                              i.      Begin work immediately; complete by August 2016.

c.       Use the time gained by a short term fix to find a more cost effective solution to complete deck replacement.  Cost goal, $1500- $3000

                                                              i.      Go back to original Proposals and ask for rationalized solution.

                                                            ii.      See other installers

                                                          iii.      Cover over, replace edge. Other compromises.

                                                           iv.      Proposals in hand by July 30. Begin works as needed, release P.O. in lots on five.

3.      Garage floor cleaning (2016)

a.      Seek professional cleaning opinion, June 2016

b.      Seek bids for work July 2016

c.       Board of Directors review and approval of best solution.

d.      Begin work August 2016
 
4.      Landscaping

a.      Establish a Landscaping committee

                                                              i.      Review contractual obligations of Kyle Marshall landscaping

                                                            ii.      Establish regular schedule for weeding, pruning, and mulching per contract.

                                                          iii.      Develop a 900 MC planting plan for both perennials and annuals.

1.      Contact a local gardener to plant and maintain flower beds.

                                                           iv.      Determine costs for the 2017 budget

                                                             v.      Implement the plan in Spring 2017 and beyond.

5.      Lobby Refresh (2017)

a.      Establish committee for decorating.

b.      Review current furnishings for replacement or restoration.

                                                              i.      Carpet, Wall hangings, Book shelves

                                                            ii.      Decorative elements

c.       Select painting contractor and any other service providers.

6.      Interior Painting(2017)

a.      Establish committee to manage project November 2016

                                                              i.      Establish scope of work, picture hanging and furniture moving.

                                                            ii.      Work areas, clean up daily, and end of job.

                                                          iii.      Phases of work, lobby, floor by floor.

                                                           iv.      Progress payments, terms & conditions, etc.

b.      Refresh paint in hallways of unit floors. Retain color scheme

                                                              i.      Identify color matches and finish.

c.       Seek commercial painters bids, January 2017

d.      Selection of painting company by BOD at the recommendation of the Committee, February , 2017

e.      Let contract, Feb 2017-

f.        Begin work March 1, 2017, completed by March 31, 2017

7.      Hallway carpeting (2016 - 2018)

a.      Shampoo hallway carpeting this year July-September?

                                                              i.      Professional carpet cleaners

                                                            ii.      M-T-W with least traffic

b.      Carpet replacement

                                                              i.      Establish committee November, 2017

                                                            ii.      Select pattern. Retaining current color scheme

                                                          iii.      Produce samples at BOD Meetings for approval from short list. January, 2018

                                                           iv.      Seek proposal from commercial carpet installers – February, 2018

                                                             v.      Let contract and begin installation March, 2018

8.      Security and Surveillance.(2018)

a.      Evaluate our current entry system for effectiveness, maintainability, and obsolescence.

                                                              i.      Consider FOB entry system

                                                            ii.      Consider camera upgrade to higher resolution versions

                                                          iii.      Consider replacement of DVR

                                                           iv.      Consider alarming forced entry

                                                             v.      Consider outside surveillance

9.      Review of Reserve Plan (2018)

a.      Establish a committee to review the current reserve plan.

                                                              i.      Identify line items that could be under or over funded.

                                                            ii.      Engage an engineering firm to update the plan if necessary.

1.      Original dated December, 2009

 

 